§ 24.20.050. Performance bond; acceptance of improvements.
Latest version.
A performance bond, to be approved by the risk manager, in the amount of 100 percent
of the estimated construction cost, shall be required from the permittee or his contractor
to provide assurance that the construction of the improvement will be completed. The
municipality will accept improved streets, avenues, alleys, ways, drives, courts and
roads after completion and upon approval of construction, and after all plan checking
and inspection fees have been paid. In addition, acceptance will be conditioned upon
posting of a warranty bond in the amount of 50 percent of the construction costs with
and in favor of the municipality assuring the repair and correction of defects that
may appear within two years of the date of acceptance. However, no street maintenance
will be performed unless the completed improvement is within a road maintenance service
area. The provisions of this section are not applicable to work performed under the
provisions of chapter 21.87, nor does anything in this section lessen the applicability of section 24.50.020.B
or chapter 24.80 to the permittee or to any other person.
(GAAB 25.15.030)
var val = document.getElementById('citecontent').innerHTML;
art.dialog.defaults.title = window.location.href;
art.dialog.data('cite', val);
art.dialog.data('homeDemoPath', '/Scripts/plus/artDialog/');
art.dialog.open('/Scripts/plus/artDialog/citeiframe.html');